Key takeaways
- 1
- Sampling, bulk and shipping take 8–10 weeks with us. Tech pack, revisions and your marketing lead-in sit on top of that.
- 2
- Bulk runs 20–25 working days and we work Monday to Saturday, so 25 working days is just over 4 calendar weeks.
- 3
- Budget one full revision round of about 3 weeks even if you hope not to need it. We include 2 rounds in sampling.
A clothing production timeline is easiest to plan backwards. Fix the launch date, then subtract each stage: marketing lead-in, shipping, bulk production, sampling, the tech pack and finally design. With us, sampling, bulk and shipping together take 8–10 weeks. Once you add a tech pack, one revision round, customs and four weeks of marketing with stock in hand, a sensible private label drop starts about 20 weeks before launch day.
Most founders plan forwards. They finish the designs, send them off and then pick a launch date based on when the factory says the goods will arrive. That's how you end up announcing a drop with no photos, or sitting on 200 hoodies for six weeks because the content wasn't ready. Working backwards forces the dates that matter to you (launch, preorders, photo shoot) to drive the dates that matter to us.
Start with a launch date you can defend
Pick a date that's tied to something. A season, a payday weekend, a collab, an event you're already doing. Then ask what needs to be true by that date: stock checked and in your hands, product photos shot, a waitlist warmed up, maybe preorders open.
We'd plan four weeks of lead-in with physical stock. That covers a shoot, editing, teaser posts, and time to catch a problem with the goods before customers do. You can compress it to two weeks if you shoot on the approved sample, but you lose the chance to photograph the real colours from the bulk dye lot.
The clothing production timeline, worked backwards
Here's a private label hoodie on one of our blanks, one print, shipped by express air. Week 0 is launch day. Our working week is Monday to Saturday, so 20 to 25 working days is about 3.5 to 4.5 calendar weeks.
| Stage | Who | Time | Weeks before launch |
|---|---|---|---|
| Marketing lead-in with stock in hand | You | about 4 weeks | -4 to 0 |
| Customs clearance and local delivery buffer | Courier, you | allow 1 week | -5 to -4 |
| Express air freight | Courier | 5 to 7 days | -6 to -5 |
| Final QC and packing | Us | 3–5 days | -7 to -6 |
| Bulk production | Us | 20–25 working days | -11 to -7 |
| Approval, deposit and fabric booking | You, us | allow 1 week | -12 to -11 |
| One revision round (buffer) | Both | allow 3 weeks | -15 to -12 |
| Sample shipped to you and reviewed | Courier, you | 4–6 days plus a few days to try it | -16 to -15 |
| Sample made | Us | 15–20 working days | -19 to -16 |
| Tech pack | Us or you | 5 working days | -20 to -19 |
| Design finalised | You | as long as it takes | before -20 |
The core of that table (sample, bulk, shipping) is the 8–10 weeks we quote. Everything else is either your time or a buffer. That's the bit people leave out.
If you've never written one, read what a tech pack is before you count those 5 working days. A tech pack missing measurements doesn't save a week. It costs one later, at sample stage.
Cut and sew and full package take longer
The table above is the fast route. For cut and sew, where we make the garment from your pattern, samples take 15–20 working days and bulk 20–25 working days. Full package, where we source every trim and fabric to your spec, runs 20–25 working days for the sample and 25–30 working days in bulk.
The bigger difference is revisions. A new pattern almost never fits perfectly first time. We include 2 revision rounds in sampling, and on cut and sew we'd plan to use both. Add another three weeks to the table and you're at roughly 24 weeks before launch.
This is what our launch planner says when someone asks how soon to start:
| Weeks until launch | Private label: start | Cut and sew: start |
|---|---|---|
| 8 weeks | This week, as a rush on an in-stock blank | Not possible |
| 12 weeks | Within 3 weeks | Not possible |
| 16 weeks | Within 7 weeks | This week |
Those start dates get goods landed by launch day. They don't include your marketing lead-in, so if you want four weeks with stock in hand, move your launch date four weeks later or start four weeks sooner.
Air or sea changes the back half of the calendar
Shipping is the one stage where you choose the length. We offer express air (5–7 days) or sea freight (25–35 days).
Sea freight adds about four weeks, plus port handling at both ends. It only really pays off at volume: express air about $5–7 per kg to the US and Canada, $4.50–6.50 per kg to the UK and EU; sea freight from about $1.50 per kg on 300 kg or more. A first run of 100 hoodies is nowhere near 300 kg, so air is usually the right call. Once you're reordering several styles at 500 pieces each, sea starts to make sense, and you plan the whole calendar a month earlier.

Customs time is less predictable than flight time. The US, for example, has suspended the $800 de minimis exemption for most shipments, so low-value parcels that used to clear informally now need a proper entry (CBP notice in the Federal Register, June 2026). That's why the table has a full week for clearance and delivery. Our guide to shipping, duties and incoterms covers who pays what.
Where do the buffers go?
Put small buffers next to the stage that causes them, not one big cushion at the end. A cushion at the end gets eaten by the first delay and nobody notices until it's gone.
The delays we see most often, roughly in order:
- Slow sample feedback. The sample arrives, sits in a drawer for ten days, then comes back with comments. Block two days in your diary for the week it lands.
- A revision you didn't plan for. Sleeve too long, print sitting too high, hood too shallow. Each remake means another sample cycle and another courier trip. Budget one even if you're confident.
- Late approval or deposit. Bulk can't start until both are in. If you need a co-founder or investor to sign off, get them to see the sample the same week.
- Holidays at the factory. Pakistan's religious holidays follow the lunar calendar, so the dates move every year. Ask your factory which closure days fall inside your production window and add them to the bulk stage.
- Holidays at your end. Couriers and customs slow down in peak season, from late November through the new year in most of our markets. If your launch is in January, your goods are travelling through the busiest weeks.
Planning more than one drop a year
Once you've run one drop, the calendar starts overlapping. While drop one is in bulk, drop two should be in sampling. While drop one is on the water or in the air, drop two's tech packs should be done.
A simple pattern that works for small labels: three or four drops a year, with each one's sampling starting the week the previous one's bulk starts. You're never waiting on us, and we're never waiting on you. If you're planning a smaller, sell-out style release, our guide to planning a limited drop covers the quantity side.
Reorders are faster because there's no sampling. A reorder of an approved style goes straight to bulk at 20–25 working days, then shipping. That's worth knowing if your best seller sells out mid-season.
What we'd do with a fixed launch date
Write the launch date at the bottom of a page. Count back four weeks for marketing, two for air freight and customs, five for bulk and packing, one for approval, three for a revision, four for the sample and its trip to you, and one for the tech pack. That's 20 weeks. If today is closer than that, cut the revision buffer only if you're on a private label blank you've already handled, or move the date.
Don't cut the marketing weeks to save the date. A drop with no photos and no build-up sells slower than the same drop a month later.
If you want us to check your dates against our current production schedule, send your launch date and styles through the quote form. We'll tell you plainly if it works. You can also see each step in order on how it works, or start with a hoodie if that's your first piece.